Capital Bond Project: Replace Site Water Supply Pipeline at South High School
|
Strategic Plan Alignment:
|
|
Enclosure
|
|
File Attachment:
|
|
Summary:
|
The Board of Education approves an expenditure of $295,513 from the Capital Bond Projects Fund for the replacement of the Site Water Supply Pipeline at South High School. The amount includes a 10% contingency. Robert Lawson is the Administrator in charge.
|
Funding:
|
The project will be funded from the Capital Bond Projects Fund.
|
Recommendation:
|
The Board of Education approves an expenditure of $295,513 and appropriates the funds from the Capital Bond Projects Fund as presented in the June 28, 2022 Board materials.
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
Robert Lawson - Executive Director of Facilities Management
|
|