Meeting Date: 2/27/2024 - 6:00 PM
Category: 11.0 CONSENT AGENDA
Type: Action
Subject: Capital Bond Project: Change Orders for the New East and Centennial High Schools Construction GMP Agreements
Strategic Plan Alignment:
GOAL 1, OBJECTIVE 5
Enclosure
File Attachment:
Summary: The Board of Education is asked to approve an expenditure of $599,646.93 from the Capital Bond Projects Fund for the additional construction costs at Centennial High School and $914,420.00 for East High School.

Robert Lawson is the Administrator in charge.
Funding: The project will be funded from the Capital Bond Projects Fund.
Recommendation: The Board of Education approves an expenditure of $599,646.93 for Centennial and $914,420.00 for East and appropriates the funds from the Capital Bond Projects Fund as presented in the February 27, 2024 Board materials.
Approvals:
Recommended By:
Signed By:
Robert Lawson - Executive Director of Facilities Management
Signed By:
David Horner - Chief Financial Officer
Signed By:
Charlotte Macaluso - Superintendent