ESSR HVAC Project: Change Order for the HVAC System Replacement at Heaton Middle School |
|
|
Strategic Plan Alignment:
|
|
Enclosure:
|
|
File Attachment:
|
|
Summary:
|
The Board of Education approves an expenditure of $496,493 from the Capital Bond Projects Fund for the replacement of the HVAC at Heaton Middle School. Robert Lawson is the Administrator in charge. |
|
|
Funding:
|
The project will be funded from the Capital Bond Project Fund. |
|
|
Recommendation
|
The Board of Education approves the expenditure of $496,493 and appropriates the funds from the Capital Bond Projects Fund as presented in the April 23, 2024 Board materials. |
|
|
Approvals:
|
Recommended By: |
Signed By: |
|
Robert Lawson - Executive Director of Facilities Management |
|