Capital Project: Haaff Elementary School Heat Exchanger Emergency Repair |
|
|
Strategic Plan Alignment:
|
|
Enclosure:
|
|
File Attachment:
|
|
Summary:
|
The Board of Education approves an expenditure of $86,074 from the Capital Projects Fund for the replacement of the boilers at Haaff Elementary School. The amount includes a 10% contingency. Robert Lawson is the Administrator in charge. |
|
|
Funding:
|
The project will be funded from the Capital Projects Fund |
|
|
Recommendation
|
The Board of Education approves an expenditure of $86,074 and appropriates the funds from the Capital Projects Fund as presented in the November 14, 2023 Board materials. |
|
|
Approvals:
|
Recommended By: |
Signed By: |
 |
Robert Lawson - Executive Director of Facilities Management |
|
Signed By: |
|
David Horner - Chief Financial Officer |
|
Signed By: |
|
Charlotte Macaluso - Superintendent |
|
|
|
|
|
|
|