Capital Bond Project: Change Orders for the New East and Centennial High Schools Construction GMP Agreements |
|
|
Strategic Plan Alignment:
|
|
Enclosure:
|
|
File Attachment:
|
|
Summary:
|
The Board of Education is asked to approve an expenditure of $599,646.93 from the Capital Bond Projects Fund for the additional construction costs at Centennial High School and $914,420.00 for East High School. Robert Lawson is the Administrator in charge. |
|
|
Funding:
|
The project will be funded from the Capital Bond Projects Fund. |
|
|
Recommendation
|
The Board of Education approves an expenditure of $599,646.93 for Centennial and $914,420.00 for East and appropriates the funds from the Capital Bond Projects Fund as presented in the February 27, 2024 Board materials. |
|
|
Approvals:
|
Recommended By: |
Signed By: |
|
Robert Lawson - Executive Director of Facilities Management |
|
Signed By: |
|
David Horner - Chief Financial Officer |
|
Signed By: |
|
Charlotte Macaluso - Superintendent |
|
|
|
|
|
|
|